BetaActiveSolarBatteryPGELBNL
513 MW hybrid in Jefferson, OR · In queue since August 2023 · Proposed COD April 2027
513 MW
Capacity
1
Components
Solar
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 8m
In Study38%
Queue EntryAug 14, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-01
Project Details
State
OR
County
Jefferson
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Round Butte - Bethel 230kV
Data Source
LBNL
No news available for this project.