— Project Summary

Queue ID
PGE-23-227
Capacity
250 MW
Technology
Wind
Status
active
Location
Jefferson, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindPGELBNL

250 MW generation in Jefferson, OR · In queue since March 2023 · Proposed COD September 2029

250 MW

Capacity

1

Components

Wind

3 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

6y 6m

In Study38%
Queue EntryMar 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-09-01

Project Details

State

OR

County

Jefferson

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

Mountain View Substation 500KV

Data Source

LBNL