400 MW hybrid in Columbia, OR · In queue since March 2023 · Proposed COD September 2028
400 MW
Capacity
1
Components
Wind
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 6m
In Study38%
Queue EntryMar 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-01
Project Details
State
OR
County
Columbia
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Trojan to Harborton 230kV line
Data Source
LBNL
No news available for this project.