— Project Summary

Queue ID
PGE-23-225
Capacity
400 MW
Technology
Wind+Battery
Status
active
Location
Columbia, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindBatteryPGELBNL

400 MW hybrid in Columbia, OR · In queue since March 2023 · Proposed COD September 2028

400 MW

Capacity

1

Components

Wind

3 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 6m

In Study38%
Queue EntryMar 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-01

Project Details

State

OR

County

Columbia

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

Trojan to Harborton 230kV line

Data Source

LBNL