— Project Summary

Queue ID
PGE-23-223
Capacity
400 MW
Technology
Wind+Battery
Status
active
Location
Washington, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindBatteryPGELBNL

400 MW hybrid in Washington, OR · In queue since March 2023 · Proposed COD September 2028

400 MW

Capacity

1

Components

Wind

3 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 6m

In Study38%
Queue EntryMar 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-01

Project Details

State

OR

County

Washington

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

West Union Substation 115kV

Data Source

LBNL

No news available for this project.