— Project Summary

Queue ID
PGE-22-119
Capacity
600 MW
Technology
Solar+Battery
Status
active
Location
Lake, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPGELBNL

600 MW hybrid in Lake, OR · In queue since January 2023 · Proposed COD December 2026

600 MW

Capacity

1

Components

Solar

3y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 11m

In Study38%
Queue EntryJan 4, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

OR

County

Lake

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

Ft. Rock 500 kV Line

Data Source

LBNL

No news available for this project.