150 MW storage in Multnomah, OR · In queue since November 2022 · Proposed COD December 2025
150 MW
Capacity
1
Components
Battery
3y 4m
In Queue
Feasibility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 1m
Schedule
3 months past proposed COD
Feasibility Study13%
Queue EntryNov 4, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
OR
County
Multnomah
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Blue Lake Substation
Data Source
LBNL
No news available for this project.