BetaActiveBatteryPGELBNL
150 MW storage in Marion, OR · In queue since April 2022 · Proposed COD December 2026
150 MW
Capacity
1
Components
Battery
3y 11m
In Queue
Feasibility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 8m
Feasibility Study13%
Queue EntryApr 14, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
OR
County
Marion
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Bethel 230 kV Substation
Data Source
LBNL
No news available for this project.