BetaActiveSolarBatteryPGELBNL
400 MW hybrid in Jefferson, OR · In queue since March 2022 · Proposed COD June 2023
400 MW
Capacity
1
Components
Solar
4 years
In Queue
Feasibility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1y 3m
Schedule
34 months past proposed COD
Feasibility Study13%
Queue EntryMar 29, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-06-15
Project Details
State
OR
County
Jefferson
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Roundbutte-Bethel 230 kV
Data Source
LBNL
No news available for this project.