200 MW storage in Clackamas, OR · In queue since May 2021 · Proposed COD January 2024
200 MW
Capacity
1
Components
Battery
4y 10m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 8m
Schedule
27 months past proposed COD
Facilities Study50%
Queue EntryMay 26, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-01-01
Project Details
State
OR
County
Clackamas
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Carver Substation
Data Source
LBNL