— Project Summary

Queue ID
PGE-21-103
Capacity
200 MW
Technology
Battery
Status
active
Location
Clackamas, OR
Region
West
Developer
IA Status
Facility Study

BetaActiveBatteryPGELBNL

200 MW storage in Clackamas, OR · In queue since May 2021 · Proposed COD January 2024

200 MW

Capacity

1

Components

Battery

4y 10m

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 8m

Schedule

27 months past proposed COD

Facilities Study50%
Queue EntryMay 26, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-01-01

Project Details

State

OR

County

Clackamas

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

Carver Substation

Data Source

LBNL

No news available for this project.