— Project Summary

Queue ID
PGE-16-060
Capacity
67 MW
Technology
Solar
Status
suspended
Location
Jefferson, OR
Region
West
Developer
IA Status
Suspended

BetaSuspendedSolarPGELBNL

67 MW generation in Jefferson, OR · In queue since September 2016 · Proposed COD November 2018

67 MW

Capacity

1

Components

Solar

9y 6m

In Queue

Suspended

IA Status

COD target: 2018

Interconnection Timeline

Total Duration

2y 2m

Suspended38%
Queue EntrySep 9, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2018-11-30

Project Details

State

OR

County

Jefferson

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

Round Butte Area @ 230 kV

Data Source

LBNL

No news available for this project.