BetaSuspendedSolarPGELBNL
150 MW generation in Jefferson, OR · In queue since July 2016 · Proposed COD January 2018
150 MW
Capacity
1
Components
Solar
9y 8m
In Queue
Suspended
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
1y 6m
Suspended38%
Queue EntryJul 6, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2018-01-01
Project Details
State
OR
County
Jefferson
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Round Butte Substation @ 230 kV
Data Source
LBNL
No news available for this project.