— Project Summary

Queue ID
PGE-16-058
Capacity
150 MW
Technology
Solar
Status
suspended
Location
Jefferson, OR
Region
West
Developer
IA Status
Suspended

BetaSuspendedSolarPGELBNL

150 MW generation in Jefferson, OR · In queue since July 2016 · Proposed COD January 2018

150 MW

Capacity

1

Components

Solar

9y 8m

In Queue

Suspended

IA Status

COD target: 2018

Interconnection Timeline

Total Duration

1y 6m

Suspended38%
Queue EntryJul 6, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2018-01-01

Project Details

State

OR

County

Jefferson

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

Round Butte Substation @ 230 kV

Data Source

LBNL

No news available for this project.