BetaSuspendedBatteryPGELBNL
100 MW storage in Marion, OR · In queue since October 2012 · Proposed COD October 2014
100 MW
Capacity
1
Components
Battery
13y 5m
In Queue
Suspended
IA Status
COD target: 2014
Interconnection Timeline
Total Duration
2 years
Suspended38%
Queue EntryOct 23, 2012
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2014-10-01
Project Details
State
OR
County
Marion
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Oxford 115 kV Substation
Data Source
LBNL
No news available for this project.