— Project Summary

Queue ID
PGE-12-052
Capacity
100 MW
Technology
Battery
Status
suspended
Location
Marion, OR
Region
West
Developer
IA Status
Suspended

BetaSuspendedBatteryPGELBNL

100 MW storage in Marion, OR · In queue since October 2012 · Proposed COD October 2014

100 MW

Capacity

1

Components

Battery

13y 5m

In Queue

Suspended

IA Status

COD target: 2014

Interconnection Timeline

Total Duration

2 years

Suspended38%
Queue EntryOct 23, 2012

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2014-10-01

Project Details

State

OR

County

Marion

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

Oxford 115 kV Substation

Data Source

LBNL

No news available for this project.