BetaSuspendedWindPGELBNL
400 MW generation in Umatilla, OR · In queue since June 2011 · Proposed COD December 2014
400 MW
Capacity
1
Components
Wind
14y 9m
In Queue
Suspended
IA Status
COD target: 2014
Interconnection Timeline
Total Duration
3y 6m
Suspended38%
Queue EntryJun 24, 2011
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2014-12-01
Project Details
State
OR
County
Umatilla
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Proposed Coyote Springs South Substation @ 500 kV
Data Source
LBNL
No news available for this project.