— Project Summary

Queue ID
PGE-11-043
Capacity
400 MW
Technology
Wind
Status
suspended
Location
Umatilla, OR
Region
West
Developer
IA Status
Suspended

BetaSuspendedWindPGELBNL

400 MW generation in Umatilla, OR · In queue since June 2011 · Proposed COD December 2014

400 MW

Capacity

1

Components

Wind

14y 9m

In Queue

Suspended

IA Status

COD target: 2014

Interconnection Timeline

Total Duration

3y 6m

Suspended38%
Queue EntryJun 24, 2011

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2014-12-01

Project Details

State

OR

County

Umatilla

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

Proposed Coyote Springs South Substation @ 500 kV

Data Source

LBNL

No news available for this project.