37 MW generation in Jefferson, OR · In queue since June 2011 · Proposed COD October 2013
37 MW
Capacity
1
Components
Other
14y 9m
In Queue
Suspended
IA Status
COD target: 2013
Interconnection Timeline
Total Duration
2y 4m
Suspended38%
Queue EntryJun 8, 2011
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2013-10-01
Project Details
State
OR
County
Jefferson
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Round Butte Substation @ 230 kV
Data Source
LBNL