BetaSuspendedWindPGELBNL
200 MW generation in Gilliam, OR · In queue since March 2011 · Proposed COD October 2015
200 MW
Capacity
1
Components
Wind
15 years
In Queue
Suspended
IA Status
COD target: 2015
Interconnection Timeline
Total Duration
4y 7m
Suspended38%
Queue EntryMar 14, 2011
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2015-10-01
Project Details
State
OR
County
Gilliam
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Proposed Cedar Spring Substation @ 500 kV
Data Source
LBNL
No news available for this project.