BetaSuspendedWindPGELBNL
500 MW generation in Gilliam, OR · In queue since August 2010 · Proposed COD January 2015
500 MW
Capacity
1
Components
Wind
15y 7m
In Queue
Suspended
IA Status
COD target: 2015
Interconnection Timeline
Total Duration
4y 5m
Suspended38%
Queue EntryAug 1, 2010
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2015-01-02
Project Details
State
OR
County
Gilliam
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Proposed Cedar Spring Substation @ 500 kV
Data Source
LBNL
No news available for this project.