400 MW generation in Sherman, OR · In queue since March 2010 · Proposed COD December 2014
400 MW
Capacity
1
Components
Wind
16 years
In Queue
Suspended
IA Status
COD target: 2014
Interconnection Timeline
Total Duration
4y 9m
Suspended38%
Queue EntryMar 23, 2010
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2014-12-01
Project Details
State
OR
County
Sherman
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Proposed Mikkalo Substation @ 500 kV