18.5 MW generation in Jefferson, OR · In queue since April 2009 · Proposed COD January 2013
18.5 MW
Capacity
1
Components
Other
16y 11m
In Queue
Suspended
IA Status
COD target: 2013
Interconnection Timeline
Total Duration
3y 9m
Suspended38%
Queue EntryApr 20, 2009
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2013-01-01
Project Details
State
OR
County
Jefferson
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Round Butte Substation @ 230 kV
Data Source
LBNL