BetaSuspendedWindPGELBNL
200 MW generation in Wasco, OR · In queue since January 2009 · Proposed COD June 2013
200 MW
Capacity
1
Components
Wind
17y 2m
In Queue
Suspended
IA Status
COD target: 2013
Interconnection Timeline
Total Duration
4y 5m
Suspended38%
Queue EntryJan 5, 2009
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2013-06-01
Project Details
State
OR
County
Wasco
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
A new location on/near Warm Springs Reservation
Data Source
LBNL
No news available for this project.