— Project Summary

Queue ID
PGE-07-026 *
Capacity
100 MW
Technology
Gas
Status
suspended
Location
Clackamas, OR
Region
West
Developer
IA Status
Suspended

BetaSuspendedGasPGELBNL

100 MW generation in Clackamas, OR · In queue since October 2007 · Proposed COD December 2011

100 MW

Capacity

1

Components

Gas

18y 5m

In Queue

Suspended

IA Status

COD target: 2011

Interconnection Timeline

Total Duration

4y 2m

Suspended38%
Queue EntryOct 9, 2007

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2011-12-01

Project Details

State

OR

County

Clackamas

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

Near Molalla Substation

Data Source

LBNL