BetaSuspendedCoalPGELBNL
385 MW generation in Morrow, OR · In queue since September 2007 · Proposed COD December 2012
385 MW
Capacity
1
Components
Coal
18y 6m
In Queue
Suspended
IA Status
COD target: 2012
Interconnection Timeline
Total Duration
5y 3m
Suspended38%
Queue EntrySep 4, 2007
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2012-12-01
Project Details
State
OR
County
Morrow
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Proposed Grassland Substation @ 500 kV
Data Source
LBNL
No news available for this project.