BetaActiveBatteryPacifiCorpLBNL
200 MW storage in Salt Lake, UT · In queue since October 2019 · Proposed COD December 2023
200 MW
Capacity
1
Components
Battery
6y 5m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
4y 2m
Schedule
27 months past proposed COD
Construction75%
Queue EntryOct 11, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
UT
County
Salt Lake
Region
West
Developer
Dominguez Grid, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Terminal substation
Data Source
LBNL
No news available for this project.