— Project Summary

Queue ID
PacifiCorp-TCS-48
Capacity
200 MW
Technology
Battery
Status
active
Location
Salt Lake, UT
Region
West
Developer
Dominguez Grid, LLC
IA Status
IA Executed

BetaActiveBatteryPacifiCorpLBNL

200 MW storage in Salt Lake, UT · In queue since October 2019 · Proposed COD December 2023

200 MW

Capacity

1

Components

Battery

6y 5m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

4y 2m

Schedule

27 months past proposed COD

Construction75%
Queue EntryOct 11, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2023-12-31

Project Details

State

UT

County

Salt Lake

Region

West

Developer

Dominguez Grid, LLC

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Terminal substation

Data Source

LBNL

No news available for this project.