40 MW hybrid in Crook, OR · In queue since September 2019 · Proposed COD May 2023
40 MW
Capacity
1
Components
Solar
6y 6m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 8m
Schedule
34 months past proposed COD
Construction75%
Queue EntrySep 19, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2023-05-30
Project Details
State
OR
County
Crook
Region
West
Developer
Three Springs Interconnection C LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Baldwin Road-Ponderosa transmission line
Data Source
LBNL