BetaActiveSolarPacifiCorpLBNL
0.15 MW generation in Benton, OR · In queue since July 2019 · Proposed COD September 2021
0.15 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
2y 2m
Schedule
56 months past proposed COD
Construction75%
Queue EntryJul 11, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2021-09-01
Project Details
State
OR
County
Benton
Region
West
Developer
Oregon State University
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Circuit 4M182 out of Hillview substation
Data Source
LBNL