BetaActiveSolarPacifiCorpLBNL
2 MW generation in Yakima, WA · In queue since October 2018 · Proposed COD December 2020
2 MW
Capacity
1
Components
Solar
7y 5m
In Queue
Facility Study
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
2y 2m
Schedule
64 months past proposed COD
Facilities Study50%
Queue EntryOct 5, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-12-31
Project Details
State
WA
County
Yakima
Region
West
Developer
OneEnergy Development, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Circuit 5Y312 out of Sunnyside substation
Data Source
LBNL