BetaSuspendedSolarBatteryPacifiCorpLBNL
300 MW hybrid in Utah, UT · In queue since November 2017 · Proposed COD November 2023
300 MW
Capacity
1
Components
Solar
8y 4m
In Queue
Suspended
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
6 years
Suspended38%
Queue EntryNov 30, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-11-30
Project Details
State
UT
County
Utah
Region
West
Developer
Longroad Development Company, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Camp Williams-Mona #1 line
Data Source
LBNL