122 MW storage in Washington, UT · In queue since December 2024 · Proposed COD December 2027
122 MW
Capacity
1
Components
Battery
1y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3 years
In Study38%
Queue EntryDec 6, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
UT
County
Washington
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Enterprise Valley substation
Data Source
LBNL
No news available for this project.