— Project Summary

Queue ID
PacifiCorp-S0032
Capacity
19.21 MW
Technology
Other
Status
active
Location
Beaver, UT
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveGeothermalPacifiCorpLBNL

19.21 MW generation in Beaver, UT · In queue since August 2024 · Proposed COD April 2026

19.21 MW

Capacity

1

Components

Geothermal

1y 7m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

1y 8m

In Study38%
Queue EntryAug 2, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-04-01

Project Details

State

UT

County

Beaver

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Tushar substation

Data Source

LBNL

No news available for this project.