BetaActiveBatteryPacifiCorpLBNL
80 MW storage in Box Elder, UT · In queue since August 2024 · Proposed COD December 2026
80 MW
Capacity
1
Components
Battery
1y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 4m
In Study38%
Queue EntryAug 2, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
UT
County
Box Elder
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Lampo substation
Data Source
LBNL
No news available for this project.