— Project Summary

Queue ID
PacifiCorp-S0022
Capacity
151.8 MW
Technology
Wind
Status
active
Location
Bingham, ID
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindPacifiCorpLBNL

151.8 MW generation in Bingham, ID · In queue since October 2023 · Proposed COD October 2027

151.8 MW

Capacity

1

Components

Wind

2y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4 years

In Study38%
Queue EntryOct 17, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-10-30

Project Details

State

ID

County

Bingham

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Basalt substation

Data Source

LBNL

No news available for this project.