BetaActiveWindPacifiCorpLBNL
151.8 MW generation in Bingham, ID · In queue since October 2023 · Proposed COD October 2027
151.8 MW
Capacity
1
Components
Wind
2y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4 years
In Study38%
Queue EntryOct 17, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-30
Project Details
State
ID
County
Bingham
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Basalt substation
Data Source
LBNL
No news available for this project.