200 MW generation in Utah, UT · In queue since October 2023 · Proposed COD September 2025
200 MW
Capacity
1
Components
Gas
2y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
1y 11m
Schedule
7 months past proposed COD
In Study38%
Queue EntryOct 17, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-09-01
Project Details
State
UT
County
Utah
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Mercer substation
Data Source
LBNL