BetaActiveSolarPacifiCorpLBNL
80 MW generation in Tooele, UT · In queue since December 2022 · Proposed COD December 2026
80 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4 years
In Study38%
Queue EntryDec 23, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
UT
County
Tooele
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Cramer Flat substation
Data Source
LBNL
No news available for this project.