— Project Summary

Queue ID
PacifiCorp-S0016
Capacity
80 MW
Technology
Battery
Status
active
Location
Sevier, UT
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPacifiCorpLBNL

80 MW storage in Sevier, UT · In queue since November 2022 · Proposed COD December 2026

80 MW

Capacity

1

Components

Battery

3y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 1m

In Study38%
Queue EntryNov 18, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

UT

County

Sevier

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Sigurd substation

Data Source

LBNL

No news available for this project.