BetaActiveBatteryPacifiCorpLBNL
58 MW storage in Washington, UT · In queue since November 2022 · Proposed COD December 2026
58 MW
Capacity
1
Components
Battery
3y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 1m
In Study38%
Queue EntryNov 18, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
UT
County
Washington
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Enterprise Valley substation
Data Source
LBNL
No news available for this project.