BetaActiveBatteryPacifiCorpLBNL
50 MW storage in Iron, UT · In queue since March 2022 · Proposed COD August 2024
50 MW
Capacity
1
Components
Battery
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 5m
Schedule
19 months past proposed COD
In Study38%
Queue EntryMar 23, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-08-30
Project Details
State
UT
County
Iron
Region
West
Developer
Granite Mountain BESS West LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Pintura substation
Data Source
LBNL