250 MW generation in Carbon, WY · In queue since March 2022 · Proposed COD January 2026
250 MW
Capacity
1
Components
Solar
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 10m
Schedule
3 months past proposed COD
In Study38%
Queue EntryMar 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-01-02
Project Details
State
WY
County
Carbon
Region
West
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Shirley Basin substation
Data Source
LBNL