— Project Summary

Queue ID
PacifiCorp-S0002
Capacity
111 MW
Technology
Solar
Status
active
Location
Carbon, WY
Region
West
Developer
PacifiCorp
IA Status
In Progress (unknown study)

BetaActiveSolarPacifiCorpLBNL

111 MW generation in Carbon, WY · In queue since March 2022 · Proposed COD January 2025

111 MW

Capacity

1

Components

Solar

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 10m

Schedule

15 months past proposed COD

In Study38%
Queue EntryMar 7, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-01-06

Project Details

State

WY

County

Carbon

Region

West

Developer

PacifiCorp

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Shirley Basin substation

Data Source

LBNL