19.9 MW generation in Jefferson, OR · In queue since November 2024 · Proposed COD December 2027
19.9 MW
Capacity
1
Components
Solar
1y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 1m
In Study38%
Queue EntryNov 27, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
OR
County
Jefferson
Region
West
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Warm Springs substation
Data Source
LBNL