— Project Summary

Queue ID
PacifiCorp-PIS094
Capacity
19.9 MW
Technology
Solar+Battery
Status
active
Location
Jefferson, OR
Region
West
Developer
PacifiCorp
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPacifiCorpLBNL

19.9 MW hybrid in Jefferson, OR · In queue since November 2024 · Proposed COD December 2027

19.9 MW

Capacity

1

Components

Solar

1y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 1m

In Study38%
Queue EntryNov 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

OR

County

Jefferson

Region

West

Developer

PacifiCorp

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Cove substation

Data Source

LBNL