— Project Summary

Queue ID
PacifiCorp-PIS089
Capacity
400 MW
Technology
Wind
Status
active
Location
Lincoln, WY
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindPacifiCorpLBNL

400 MW generation in Lincoln, WY · In queue since October 2024 · Proposed COD October 2028

400 MW

Capacity

1

Components

Wind

1y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4 years

In Study38%
Queue EntryOct 31, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-01

Project Details

State

WY

County

Lincoln

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Naughton-Ben Lomond #2 transmission line

Data Source

LBNL