BetaActiveSolarBatteryPacifiCorpLBNL
300 MW hybrid in Iron, UT · In queue since December 2023 · Proposed COD February 2026
300 MW
Capacity
1
Components
Solar
2y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 2m
Schedule
2 months past proposed COD
In Study38%
Queue EntryDec 22, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-02-09
Project Details
State
UT
County
Iron
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Three Peaks substation
Data Source
LBNL
No news available for this project.