— Project Summary

Queue ID
PacifiCorp-PIS031
Capacity
199 MW
Technology
Solar
Status
active
Location
Emery, UT
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPacifiCorpLBNL

199 MW generation in Emery, UT · In queue since April 2023 · Proposed COD December 2026

199 MW

Capacity

1

Components

Solar

2y 11m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 8m

In Study38%
Queue EntryApr 14, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

Project Details

State

UT

County

Emery

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Camp Williams-Four Corners transmission line

Data Source

LBNL

No news available for this project.