199.9 MW storage in Klamath, OR · In queue since June 2022 · Proposed COD December 2026
199.9 MW
Capacity
1
Components
Battery
3y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 6m
In Study38%
Queue EntryJun 24, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-15
Project Details
State
OR
County
Klamath
Region
West
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Snow Goose substation
Data Source
LBNL