— Project Summary

Queue ID
PacifiCorp-PIS005
Capacity
48 MW
Technology
Gas
Status
active
Location
Lincoln, WY
Region
West
Developer
PacifiCorp
IA Status
IA Executed

BetaActiveGasPacifiCorpLBNL

48 MW generation in Lincoln, WY · In queue since May 2022 · Proposed COD May 2022

48 MW

Capacity

1

Components

Gas

3y 10m

In Queue

IA Executed

IA Status

Signed May 2023

Interconnection Timeline

Queue → IA

1 year

Total Duration

1 year

Schedule

47 months past proposed COD

Construction75%
Queue EntryMay 12, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementMay 3, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2022-05-16

Project Details

State

WY

County

Lincoln

Region

West

Developer

PacifiCorp

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Naughton substation

Data Source

LBNL