BetaActiveWindPacifiCorpLBNL
199 MW generation in Cowlitz, WA · In queue since May 2024 · Proposed COD December 2027
199 MW
Capacity
1
Components
Wind
1y 10m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 7m
Pre-Study0%
Queue EntryMay 15, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
WA
County
Cowlitz
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Cardwell - Merwin transmission line
Data Source
LBNL