— Project Summary

Queue ID
PacifiCorp-C4-095
Capacity
49.9 MW
Technology
Solar+Battery
Status
active
Location
Crook, OR
Region
West
Developer
IA Status

BetaActiveSolarBatteryPacifiCorpLBNL

49.9 MW hybrid in Crook, OR · In queue since May 2024 · Proposed COD November 2027

49.9 MW

Capacity

1

Components

Solar

1y 10m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 6m

Pre-Study0%
Queue EntryMay 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-11-30

Project Details

State

OR

County

Crook

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Baldwin Road substation

Data Source

LBNL