8 MW generation in Bighorn, MT · In queue since May 2024
8 MW
Capacity
1
Components
Hydro
1y 10m
In Queue
—
IA Status
Interconnection Timeline
Total Duration
1y 10m
Pre-Study0%
Queue EntryMay 15, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
MT
County
Bighorn
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Yellowtail substation
Data Source
LBNL