1,280 MW hybrid in Klamath, OR · In queue since May 2024 · Proposed COD May 2031
1,280 MW
Capacity
1
Components
Solar
1y 10m
In Queue
—
IA Status
COD target: 2031
Interconnection Timeline
Total Duration
7 years
Pre-Study0%
Queue EntryMay 15, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2031-05-01
Project Details
State
OR
County
Klamath
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Corral - Snow Goose transmission line
Data Source
LBNL