BetaActiveSolarBatteryPacifiCorpLBNL
400 MW hybrid in Utah, UT · In queue since May 2024 · Proposed COD December 2027
400 MW
Capacity
1
Components
Solar
1y 10m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 7m
Pre-Study0%
Queue EntryMay 15, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
UT
County
Utah
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Camp Williams - Mercer - Mona #2 transmission line
Data Source
LBNL
No news available for this project.