— Project Summary

Queue ID
PacifiCorp-C4-089
Capacity
400 MW
Technology
Solar+Battery
Status
active
Location
Utah, UT
Region
West
Developer
IA Status

BetaActiveSolarBatteryPacifiCorpLBNL

400 MW hybrid in Utah, UT · In queue since May 2024 · Proposed COD December 2027

400 MW

Capacity

1

Components

Solar

1y 10m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 7m

Pre-Study0%
Queue EntryMay 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

UT

County

Utah

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Camp Williams - Mercer - Mona #2 transmission line

Data Source

LBNL

No news available for this project.