— Project Summary

Queue ID
PacifiCorp-C4-087
Capacity
20 MW
Technology
Other
Status
active
Location
Douglas, OR
Region
West
Developer
IA Status

BetaActiveOtherPacifiCorpLBNL

20 MW generation in Douglas, OR · In queue since May 2024 · Proposed COD June 2026

20 MW

Capacity

1

Components

Other

1y 10m

In Queue

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 1m

Pre-Study0%
Queue EntryMay 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-30

Project Details

State

OR

County

Douglas

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Roseburg Lumber Tap

Data Source

LBNL

No news available for this project.